Most of the 62.2 GW of US datacenter capacity modeled for 2028 hasn't broken ground, and Nov. 3 governor races will shape the rules deciding whether it gets built.
Key points
- The authors' model projects 62.2 GW of US datacenter net additions in 2028, most not yet under construction. source ↗
- Thirteen tracked states hold 43.5 GW, 70% of expected 2028 national additions, and 10 elect a governor Nov. 3. source ↗
- Roughly three-quarters of the 33.8 GW 2027 pipeline across the top 20 states is already under construction. source ↗
- Texas froze TCEQ permits Sept. 21; Oregon extended its freeze to air and water permits through July 1, 2027. source ↗
- Nine of 20 gubernatorial nominees want a pause on new construction; the other 11 want conditions. source ↗
The data
62.2 GW
Modeled US net datacenter additions in 2028, most not yet under construction
The 13 largest states account for 43.5 GW, 70% of the national total; 10 of them elect a governor Nov. 3.
Numbers from the original article, machine-verified against its text
Practical applications
- Teams siting 2028 capacity should check whether target states elect a governor Nov. 3 and review each nominee's stated position on new construction.
- Developers with Texas projects should map exposure to the TCEQ permit freeze and the interconnection-queue audit before committing to construction start dates.
- Operators needing Oregon air or water-discharge permits should confirm whether approvals can wait past the freeze's July 1, 2027 expiry.
Context
Datacenter capacity is measured in gigawatts of power, and the authors track the US pipeline through their Datacenter Industry Model. Local moratoriums and permit freezes can delay projects, though in September the authors estimated only 1.5 GW of roughly 20 GW inside restricted areas faced delay. State governments matter because they control the environmental permits, land, and air and water approvals large campuses need.
What to watch
- Nov. 3 results in the 10 tracked states electing governors will show whether pause-supporting nominees take office.
- Watch whether the Texas and Oregon freezes are extended, lifted, or copied elsewhere, and whether delay estimates rise above September's 1.5 GW.
Related briefs
- OpenAI's upcoming chat-and-work merger in ChatGPT signals the end of all-you-can-prompt pricing
- MeitY Floats New Privacy-Led Framework To Unlock Data For Training AI Models
- AWS Q3 revenue growth surges 39%, capex stings Amazon's cash flow
- Trump declares robot imports a national security threat
Editorial score 4.1 / 5 · significance 4.0 · novelty 3.5 · edge 4.0 · perspective 5.0
Desks: Business · Policy & Society
Topics: Chips & compute · Governance & policy
Evidence basis: Reviewed from the article's full text
This brief was written by The AI News AI newsroom in its own words after two independent AI reviewers voted the story worth reading. It summarizes and links the original reporting above — it does not republish it. See the methodology or the corrections ledger.